Swift Network News Header

Construction is underway on the Swift Green Line, Community Transit's second bus rapid transit route.

Work has started on the 34 Swift stations that will line the corridor between Bothell and Boeing. Construction is also underway on a new transit center near Boeing and a road widening project near the I-5 overpass along 128th Street in south Everett. The Swift Green Line is scheduled to open for service in early 2019.

The Swift Network News newsletter is published weekly to provide the latest construction updates about the Swift Green Line, which includes these projects:


Swift Network News

Issue 42, Volume 2 | May 25, 2018

Bothell Everett Hwy at Mill Creek Rd.In this issue:

  • Swift Green Line Stations: Busy Week for Southbound Station at 164th

  • Community Transit LiveNext Webcast to Feature Special Guest

  • Seaway Transit Center: Concrete Bus Pads Installed on Seaway Blvd.

  • 128th Street: Concrete, Electrical Work Continues on East Side of I-5

  • Swift Blue Line News: Station Painting to Begin on June 4

  • Construction Overview: Station Construction is Divided into Four Areas With Work Done in Stages
View this issue online now
Subscribe to receive this newsletter here.

Issue 41, Volume 2 | May 18, 2018

Bus under new signs on 128thIn this issue:

  • Swift Green Line Stations: Weekend Lane Closures in Area 2; In-Lane Concrete Pads Designed to Withstand Frequent Swift Service

  • 128th Street: Traffic Signs Installed Over Bus-Only Lane

  • Seaway Transit Center: Concrete Flow Continues in Future Transit Center

  • Community Transit LiveNext Webcast: May 29 at 4 p.m.

  • Swift Blue Line News: Swift Blue Line Stations Prepare for Paint

  • Construction Overview: Station Construction is Divided into Four Areas With Work Done in Stages
View this issue online now
Subscribe to receive this newsletter here.

Issue 40, Volume 2 | May 11, 2018

Swift Station Progress Collage May 11 2018In this issue:

  • Swift Green Line Stations: Steel Frame Installation Almost Complete in Area 1

  • 128th Street: Widening Project Stays Focused on East of I-5

  • Seaway Transit Center: Mechanical Building and Concrete Making Good Progress

  • Community Transit LiveNext Webcast: May 29 at 4 p.m.

  • Swift Blue Line News: Blue Line Stations to be Repainted

  • Construction Overview: Station Construction is Divided into Four Areas With Work Done in Stages
View this issue online now
Subscribe to receive this newsletter here.



Past Issues of Swift Network News

Swift Network News

Issue 42, Volume 2 | May 25, 2018
Issue 41, Volume 2 | May 18, 2018
Issue 40, Volume 2 | May 11, 2018
Issue 39, Volume 2 | May 4, 2018
Issue 38, Volume 2 | April 27, 2018
Issue 37, Volume 2 | April 20, 2018
Issue 36, Volume 2 | April 16, 2018
Issue 35, Volume 2 | April 6, 2018
Issue 34, Volume 2 | March 30, 2018
Issue 33, Volume 2 | March 23, 2018
Issue 32, Volume 2 | March 16, 2018
Issue 31, Volume 2 | March 9, 2018
Issue 30, Volume 2 | March 2, 2018
Issue 29, Volume 2 | February 26, 2018
Issue 28, Volume 2 | February 16, 2018
Issue 27, Volume 2 | February 9, 2018
Issue 26, Volume 2 | February 2, 2018
Issue 25, Volume 2 | January 26, 2018
Issue 24, Volume 2 | January 19, 2018
Issue 23, Volume 2 | January 11, 2018
Issue 22, Volume 2 | January 5, 2018
Issue 21, Volume 2 | December 28, 2017
Issue 20, Volume 2 | December 15, 2017
Issue 19, Volume 2 | December 8, 2017
Issue 18, Volume 2 | December 1, 2017
Issue 17, Volume 2 | November 17, 2017
Issue 16, Volume 2 | November 10, 2017
Issue 15, Volume 2 | November 3, 2017
Issue 14, Volume 2 | October 26, 2017
Issue 13, Volume 2 | October 19, 2017
Issue 12, Volume 2 | October 12, 2017
Issue 11, Volume 2 | September 28, 2017
Issue 10, Volume 2 | September 15, 2017
Issue 9, Volume 2 |August 31, 2017
Issue 8, Volume 2 |August 18, 2017
Issue 7, Volume 2 |August 7, 2017
Issue 6, Volume 2 | July 21, 2017
Issue 5, Volume 2 | July 7, 2017
Issue 4, Volume 2 | June 23, 2017
Issue 3, Volume 2 | June 9, 2017
Issue 2, Volume 2 | May 25, 2017
Issue 1, Volume 2 | May 11, 2017